Material list

slab 10 × 10 ft, 4 in thick, 10% waste

  • 62 × 80 lb bags of concrete mix
Concrete volume
1.23 cu yd (33.3 cu ft)
With 10% waste
1.36 cu yd (36.7 cu ft)
Bags at standard yield
123 × 40 lb, or 82 × 60 lb, or 62 × 80 lb
Ready-mix order
1.5 cu yd
Bag yield used
0.6 cu ft per bag

That is more than about 45 bags of 80 lb. For pours over a cubic yard, compare the price of ready-mix delivery.

How it works

Pick a shape and enter its dimensions. A slab takes length, width and thickness; a footing takes length, width and depth; a round column or post hole takes diameter and height; steps take the number of steps, riser height, tread depth and width. Steps are counted as solid blocks poured on grade, with the lowest step one riser tall.

The calculator finds the volume of one item, multiplies by the quantity and adds a 10% waste allowance (you can change it). The result is shown net and with waste in cubic feet and cubic yards, or in cubic metres when you switch to metric.

Bag counts use the yield printed on standard bags: 0.60 cubic feet from an 80 lb bag, 0.45 from a 60 lb bag and 0.30 from a 40 lb bag. Metric bags of 20, 25 and 30 kg use the same yield per kilogram. Bags are rounded up to whole bags, because that is how they are sold.

Ready-mix is rounded up to the nearest 0.25 cubic yard or 0.25 cubic metre. The calculator warns when a slab is thinner than 3.5 inches, when a bag order is over one cubic yard (worth switching to ready-mix), and reminds you that footings, columns and steps are structural work.

The formula

  • Slab: length × width × thickness
  • Footing: length × width × depth
  • Column, tube or post hole: π × (diameter ÷ 2)² × depth
  • Solid steps (n steps): width × run × rise × n × (n + 1) ÷ 2
  • Order = volume × (1 + waste %); 1 cubic yard = 27 cubic feet
  • Bags = order ÷ bag yield, rounded up. Standard yield: 80 lb = 0.60 cu ft, 60 lb = 0.45 cu ft, 40 lb = 0.30 cu ft (25 kg ≈ 11.7 L); enter your bag's own yield to override
  • Ready-mix is rounded up to the next ¼ cubic yard (or ¼ m³)

Worked examples

  1. Slab 12 × 12 ft, 4 in thick with 10% waste: 1.78 cu yd (48 cu ft) before waste, 52.8 cu ft after. Buy:

    • 88 × 80 lb bags of concrete mix
  2. 6 × round 12 in column or hole, 48 in deep with 10% waste: 0.7 cu yd (18.8 cu ft) before waste, 20.7 cu ft after. Buy:

    • 47 × 60 lb bags of concrete mix
  3. Slab 4 × 3 m, 100 mm thick with 10% waste: 1.2 m³ before waste, 1.32 m³ after. Buy:

    • 1.5 m³ of ready-mix concrete

Tips

  • Check the yield printed on your bags and enter it as the bag yield if it differs; high-strength and fast-setting mixes often yield less than the standard figure.
  • Round measurements up rather than down; a spare bag is easier to deal with than a short pour.
  • Ready-mix suppliers have their own minimum loads, so confirm the amount with them before ordering.
  • Size footings, columns and steps from your plans and local building code, or ask a qualified professional.

Questions

How many 80 lb bags make a cubic yard?

45. Each 80 lb bag yields 0.60 cubic feet and a cubic yard is 27 cubic feet, so 27 divided by 0.60 is 45.

How many 60 lb or 40 lb bags make a cubic yard?

60 bags of 60 lb mix (0.45 cubic feet each) or 90 bags of 40 lb mix (0.30 cubic feet each), before waste.

How much concrete does a 25 kg bag make?

About 0.0117 cubic metres, or 11.7 litres, using the same yield per kilogram as the US bags. A 20 kg bag gives about 9.4 litres and a 30 kg bag about 14 litres.

How much concrete do I need for a 10 ft by 10 ft slab 4 inches thick?

About 1.23 cubic yards net (33.3 cubic feet). With the default 10% waste the order is 36.7 cubic feet, which is 62 eighty-pound bags or 1.5 cubic yards of ready-mix.

Does the calculator tell me how thick my slab or footing should be?

No. It only warns when a slab is under 3.5 inches thick and flags footings, columns and steps as structural. Thickness and sizes must come from your plans, your local building code or a qualified professional.

The full method, every constant and its source are published with the calculator code. Found a result that looks wrong? Email yardlist@lobbykit.net with the share link.